UCR fee schedule
Six brackets by power-unit count, each with one all-in total for the registration year.
Revised
Contents
01Schedule
Six brackets by power-unit count, for registration year 2026.
- 0–2 vehicles
- $96.00
- 3–5 vehicles
- $223.00
- 6–20 vehicles
- $426.00
- 21–100 vehicles
- $1,263.00
- 101–1,000 vehicles
- On requestquoted after review
- 1,001+ vehicles
- On requestquoted after review
02Composition
Each band carries one all-in price for the registration year. The figure quoted is the figure charged; nothing is added at checkout, and there is no renewal billing. The spread between the smallest and largest band is set by the states, not by us — our own work does not scale with fleet size.
03Bracket boundaries
The schedule is stepped, and the range from the lowest bracket to the highest spans three orders of magnitude. A single power unit either side of a boundary can change the total materially, which is why the count is confirmed rather than assumed from the register.
| Power-unit counting methodology | Method A: the latest MCS-150. Method B: the twelve-month measuring period. Definitions and edge cases. |
|---|---|
| UCR and BOC-3: the distinction | Separate obligations, separate authorities, separate frequencies. A row-by-row comparison. |
| The UCR annual cycle | Season opening, due date, enforcement date, and the consequences of late registration. |
Roadway Compliance is a private filing service. Not affiliated with the FMCSA, the UCR Plan, or any government agency.